4.3 MoC Approval
4.3.1 Who has Authority to Approve MoC?
| What? | Vessel | Office |
|---|---|---|
| Changes to Personnel | Technical Superintendent in consultation with Crew Manager | HSSEQ Manager Note: - The MD must approve all requirements for Senior Management changes |
| Changes to Ship / Shore Working Arrangements | Technical Superintendent in consultation with Crew Manager | HSSEQ Manager |
| Changes to Structure/ Equipment | Technical SuperintendentNote: - Subject to client approval - For projects above USD 50K get HSSEQ Manager approval | Managing Director |
| Changes to External Party Documentation | Technical Superintendent | HSSEQ Manager |
| Major Projects | Technical Superintendent | Managing Director |
| Changes Not in the Above CategoriesNote: Decision regarding non-availability of a process/material/person that may affect the safety of life, environment, and property at sea. | HSSEQ Manager | Managing Director |
4.3.2 MoC Approval Procedure
The Approving Authority must do this procedure on receiving the request.
Note: Refer - 4.3.1 Who has Authority to Approve MoC?
- Review the change request
- Verify the minimum authority level
- Review the implications of change
- Review and approve the permit
- Review the Risk assessment
- Check the RA / JSA has planned to mitigate all foreseeable risks
- Review the proposed training requirements are comprehensive
- On completion of the review:
- Approve or Reject the change
Note: The personal directly involved with or proposing the change must not review the request
- Review the change request
- Set a target date for completion of:
- Project risk mitigating tasks
- Individual risk mitigating
- Set a target date for completion of:
- If the change is temporary:
- Define the validity period of the temporary status
Note:Re-view, updated and re-approved the change request, if target date not met.
- Ensure they are:
- Aware of the change
- Understand the change
- Aware of the likely impact due to change
Note: This includes vessels contracted in and contract staff, who are required to perform tasks in compliance with our policies and procedures.